Step-up: 160kV (Standby) -> 200kV (Operation)
- Confirm that the accelerating voltage is in the standby state (160kV) and the dark current (Beam Current when the electron beam is stopped) is 80±2uA.
- [TEM Center: Upper menu] Control → Beam
- Display Beam Controller (for JEM Administrators)
- Check HT Voltage / Current HT: (160kV)
- If stopped, contact the administrator (Do not step up)
- Check Filament / Beam Current HT: (80±2uA)
- If not stable, contact the administrator (Do not step up)
- [TEM Center: Upper menu] Control → Beam
- Step up slowly to avoid discharge
- [TEM Center: Upper menu] Application → HT Scheduling
- Display HT Scheduling
- Set the step-up conditions in Liner Step
- Step Volt = 0.1kV, Interval Time = 3s
- [TEM Center: Upper menu] Application → HT Scheduling
Step-down: 200kV (Operation) -> 160kV (Standby)
- Set the accelerating voltage to 160kV (standby state)
- [TEM Center: Upper menu] Control → Beam
- Display Beam Controller (for JEM Administrators)
- HT Voltage: Select [160]
- Check Filament / Beam Current HT: (80±2uA)
- If not stable, contact the administrator
- [TEM Center: Upper menu] Control → Beam